Howe Drive 2011
second phase
Wednesday, July 27, 2011
mixing up the grout
filling in the openings
laying the waste water pipes
covering up the pipes
where's the pipe?
Tuesday, July 26, 2011
putting the beams in place
Monday, July 25, 2011
shortening up the support beams
laying the water pipes
closing up some of the water trenches
Tuesday, July 19, 2011
the last of the waste pipes
covering the waste pipes
Monday, July 18, 2011
things are dug up for the water lines
four houses are done
looking for the inlet for the water
Thursday, July 14, 2011
getting the pipes ready
last of the sanitary waste pipes
Wednesday, July 13, 2011
sealing around the pipes
getting ready for the sanitary sewer hookups
another day of trenching
Tuesday, July 12, 2011
moving the sheds out of the way for the sanitary sewers
today was the day for installing sanitary sewers
over looking the work from high above
connecting the pipes
Monday, July 11, 2011
more fill
two houses done
Friday, July 8, 2011
a continuation of the plumbing
getting ready for the underground services
the start of the french drain
filling in the french drain with stone
Thursday, July 7, 2011
the waste pipes layed out on the first house
greasing the bolts
getting ready to water proof the walls
finishing up the last of the trenches
Wednesday, July 6, 2011
Pondering the layout of the waste system
Tuesday, July 5, 2011
doing the underground electrical
one of the many loads of fill
digging out for the waste and drainage pipes
opps
covering over the drainage pipe